CLIENT: QGC
LOCATION: Chinchilla, QLD
VALUE: $1 million – $5 million
DURATION: September 2014 – April 2015

Shamrock Civil was engaged by QGC Pty Ltd (QGC) to undertake the construction of the upstream remediation for the Kenya Large Pond in Chinchilla, QLD.

The scope of works involved:

  • Earthworks;
  • Embankment cut and full;
  • Pavement;
  • Environmental Management;
  • Safety Management; and
  • Client Management.

The project team worked proactively with the client to identify and resolve numerous site issues, that had the potential to cause project overruns in both cost and time.

The project had an outstanding safety record, with zero LTI’s recorded. The design and construction was on time and within budget.