Kenya Location Chinchilla QLD Client QGC Duration of Project September 2014 - April 2015 Contract Value $3 Million Shamrock Civil Engineering were engaged by QGC Pty Ltd (QGC) to undertake…
GLNG Location Condamine QLD Client Origin Energy Duration of Project December 2008 - December 2009 Contract Value $13.3 Million The Evaporation Pond B forms part of the Talinga Development Coal…
GLNG Location Roma QLD Client McNab Duration of Project July 2011 - February 2012 Contract Value $4.1 Million The project was situated at two locations Roma and Fairview. The Fairview…
APLNG Location Miles QLD Client Enerstream JV Duration of Project January 2012 - August 2012 Contract Value $30.2 Million Shamrock Civil were contracted by Enerstream JV to perform the early…
McConnell Location Roma QLD Client McNab Duration of Project January 2012 - February 2012 Contract Value $1 Million The McConnel Dowell Laydown project is located at the Roma Hub 02…
Bellevue 3+1 Location Surat Basin QLD Client Transfield Services Clough JV Duration of Project November 2012 - July 2013 Contract Value $27 Million The Matilda John, Kate & McNulty FCS’s…
Cameby Downs Location Miles QLD Client Yancoal Duration of Project May 2014 - July 2014 Contract Value $1.7 Million Shamrock Civil Engineering was contracted by Yancoal to carry out the…
Spring Gully Development Location Roma QLD Client Origin Energy Duration of Project June 2008 - December 2008 Contract Value $3 Million The Spring Gully development project is located approximately 80km…