Shamrock Civil was awarded the project which involved the upgrade of the Jackson Road and Sadlier Street intersection within Gallipoli Barracks at Enoggera.
Scope of Work
-
Locate and pothole all existing underground & overhead services to confirm all depths, heights and locations
-
Removal of 14 existing trees on the northern side of Jackson Road and new replacement planting at a ratio of 1:10 (1 removed: 10 replaced)
-
Excavation of earth, kerb, footpath, and vegetation that fall within thewidening section
-
Excavation, treatment and disposal of PFAS contaminated spoil
-
Construction of 2 new pavements: rigid (reinforced concrete) & flexible (gravel and asphalt surfacing)
– 182m2 double reinforced 250mm 40Mpa
– 152m2 flexible pavement including 200mm 2.5 Road base, 165mm2.3 Road base, 150mm Type 2.1 Road base & 50mm Asphalt
-
Construction of new pavement drainage including subsurface drainage, kerb & channel, storm water gully pit and manhole
-
Construction of new footpath, pram ramps and turfed verge
-
Relocate existing fire hydrant and remove existing watermain valve to facilitate new road widening
-
Relocate existing signage and installation of new signage and pavement linemarking