CLIENT: Logan City Council
VALUE: $1 million – $5 million
DURATION: Apr 2014 – Feb 2015
Shamrock Civil was engaged by Logan City Council to design and construct a new two lane composite modular bridge structure to replace the existing Edward O’Neill timber bridge, crossing Teviot Brook Stream, Jimboomba.
Scope of Works
- Bridge construction designed with an overall length of 48 metres plus a 3m relieving slab on each end;
- Construction of temporary piling access; and Pavement works.
Despite challenging weather conditions, the project team delivered the scope of works on time for the Logan City Council.