CLIENT: Lendlease
VALUE: $1 million – $5 million
DURATION: January 2016 – June 2016

Shamrock Civil Engineering were awarded the contract to construct the RNA Detention Tank Stormwater, as part of the RNA Showgrounds Redevelopment for Lendlease.

The scope of works were as folllows:

  • Stormwater works associated with the construction of the detention tank
  • Installation of triple coil culverts including auger boring and pipe jacking and construction of large concrete chambers
  • Installation of stormwater RCP’s ranging from 375mm to 750mm and associated manhole structures
  • Removal & replacement of 600 virtified clay sewer pipe including temporary proping works certified by RPEQ and modifications to deep manhole structure and stub.