Buddhist Vihara
Temple Goodna Stage 1
Location
Goodna QLD
Client
Buddhist Vihara (Temple) of Queensland Inc. (BVOQLD)
Duration of Project
August 2019 – January 2020
Contract Value
$1.9 Million
Shamrock Civil was contracted to deliver the upgrades and improvements of the Buddhist Vihara Temple in Goodna, as part of the Stage 1 development.
Scope of Work
-
Site clearing
-
Bulk earthworks (cut to fill & import)
-
Stormwater pipes and structures (including a 238kL stormwater detentiontank system)
-
Concrete kerb & channel
-
Concrete pathways (including PWD compliant ramp)
-
Roadworks, pavement & carpark construction (including asphalt)
-
Boulder retaining walls (design & construct)
-
Fencing (chain wire & acoustic fencing)
-
Electrical mains & internal electrical services
-