Melbourne Regional Landfill (MRL) Early Works & Cell 4A Construction

Melbourne Regional

Landfill (MRL) Early Works & Cell 4A Construction

Location

Ravenhall VIC

Client

Cleanaway Solid Waste Pty Ltd

Duration of Project

February 2018 – October 2018

Contract Value

$5.2 Million

Shamrock Civil Engineering was awarded this project, following on from our high-quality work and successful construction of previous cells. Cell 4A involved the construction of a new landfill cell adjacent to the existing operating landfill facility in Ravenhall, Melbourne.

Scope of Work

  • Bulk earthworks consisted of 6,700m3 of subgrade cut, 95,000m3 of subgrade fill and 32,700m3 of clay fill
  • Lining works consisted of the installation of 65,000m2 of HDPE, 65,000m2 of geo-synthetic clay liner (GCL), 65,000m2 of protection geo-textile (cushion) and 55,000m2 of separation geo-textile
  • The leachate collection system consisted of the supply and installation of1,700lm of 160mm dia HDPE pipes and 2 x 500mm dia leachate riser pipes approx 15m, 3,000 m3 of protection soils and placement of 18,500m3 leachate aggregate
  • 7,500m2 drainage composite

Project Complications & Achievements

At the request of Cleanaway, Shamrock Civil accelerated the construction program multiple times, with tight deadlines successfully met. Shamrock Civil also provided works and services in other areas of the site to assist operations and help improve the site. Shamrock Civil commenced the Early Works package (rock breaking) for the next cell, while still completing Cell 4A utilising the same project management team. Shamrock Civil successfully delivered this project with zero LTIs or environmental issues.