New Chum
Landfill - Cell 3A
Location
New Chum, QLD
Client
Cleanaway
Duration of Project
January 2019 – July 2019
Contract Value
$3.6M
Shamrock Civil Engineering was engaged by Cleanaway on the New Chum Landfill project, to undertake the construction of cell 3A. This follows on from the successful delivery of cell 4B at New Chum and a number of cell construction projects in Victoria.
Scope of Work
-
Bulk earthworks
-
Geo-synthetics lining work
-
Leachate collection system
-
Concrete works to construct a fully functional landfill cell.
-
10,919m3 of subgrade preparation
-
18,450m3 of engineering fill
-
1100m of anchor trench construction
-
61,700m2 deployment of GCL
-
61,700m2 deployment of HDPE
-
Deployment of protection and separation geotextile
-
Construction of leachate collection system, including perforated polyethylene pipes, leachate sump riser, 300mm thick aggregate layer & separation geotextile materials.