New Youth Detention Centre
Brisbane Civil & Bulk Earthworks
Location
Wacol, QLD
Client
Department of Housing and Public Works
Duration of Project
September 2019 – September 2020
Contract Value
$6.6M
Shamrock Civil was awarded this project which included additional works to the current Youth Detention Centre at Wacol.
Scope of Work
-
Demolition including removing pavement and inground services
-
Site clearing including tree removal and topsoil strip
-
Bulk earthworks including cut to spoil and import fill, sub-base and base course pavements, stormwater RCP’s, culverts and pits
-
Electrical conduit installation
-
Combined services trench. Crane pads
-
Temporary works including contractors carpark.
-
Strip 33,587m2 of topsoil
-
Cut to spoil 31,265m3 of spoil
-
Rock excavation 5,488m3
-
225 Pipes – 275m
-
300 RCP’s – 460m
-
375 RCP’s – 110m
-
450 RCP’s – 86m
-
525 RCP’s – 48m
-
750 RCP’s – 69m
-
Pits – 54
-
2 large custom access chambers
-
4,500m2 of two coat seal carpark
-
1,500me of asphalt pavements
-
Temporary access tracks
-
1,000m2 crane pads