Youth
Detention Centre
Location
Wacol QLD
Client
Department of Housing and Public Works
Duration of Project
September 2019 – September 2020
Contract Value
$6.6 Million
Shamrock Civil was awarded the civil and bulk earthworks project for the new youth detention centre in Wacol.
Scope of Work
-
Demolition including removing pavement and inground services
-
Site clearing including tree removal and topsoil strip
-
Bulk earthworks including cut to spoil and import fill, Sub-base and base course pavements, Stormwater RCP’s, culverts and pits
-
Electrical conduit installation
-
Combined services trench
-
Crane Pads
-
Temporary works including contractors carpark
-
Strip 33,587m2 of topsoil
-
Cut to spoil 31,265m3 of spoil
-
Rock excavation 5,488m3
-
225 Pipes – 275m
-
Large custom access chambers
-
4,500m2 of two coat seal carpark
-
1,500me of asphalt pavements
-
Temporary access tracks
-
1,000m2 Crane Pads